The project is green. The extra work is not covered. | KaiMesh

A third integration reaches the delivery plan, but the signed agreement only includes two. KaiMesh connects the request, the estimate, and the missing amendment before the work starts.

KaiMesh product walkthrough · IT-01. Follow the source records, review the proposed response, and verify the outcome.

The source records

Signed scope

Two integrations included. Additional integrations require a signed amendment.

Record: SOW-1

Client request + estimate

A third integration adds 120 estimated hours. A request is not commercial approval.

Record: REQ-1 · EST-1

Delivery plan + agreements

The task is scheduled to start. The agreement index contains no signed amendment.

Record: TASK-1 · AMEND-INDEX

What KaiMesh surfaces

Delivery is about to absorb work the customer has not agreed to pay for.

A response to review

Prepare the $24,000 scope amendment for review. Hold only the additional integration until the customer signs; continue the original work.

Follow the calculation

120 additional hours × $110 loaded hourly cost = $13,200. If absorbed, forecast margin falls from 35% to 29.5% on the $240,000 fixed fee.

Verify what happened

Check for the signed amendment, approved task release, and later actual costs. A proposed fee is not collected revenue.